Project Implementation
The project is divided into five lots under three contracts:
Lot 1: Millennium Highway to Cul De Sac Roundabout
Contractor: C.O. Williams Construction Limited
Length: Approximately 7 km
Current Status: 90% physical completion
Expected Completion: May 30, 2025
Lot 2B: Anse La Raye Bridge
Contractor: O.B. Sadoo Engineering Services Limited
Current Status: 30% physical completion
Expected Completion: August 31, 2025
Lot 2A/3A/3B: Cul De Sac to Soufriere Bridge
Contractor: Namalco Construction Services Ltd
Length: Approximately 34 km
Current Status: 24% physical completion
Expected Completion: November 30, 2025